Worked example: pricing the labour for a bathroom
A bathroom with 18 m² of wall tiles at £45 per m² and a 4 m² floor at £50 per m². The shower needs tanking (£250), the floor needs levelling (4 m² at £25 per m²) and the trims and sealing come to £60. You lay about 8 m² a day on walls and floors, and your day rate is £300.
| Step | Working | Result |
|---|---|---|
| Tiling labour | 18 m² × £45 + 4 m² × £50 | £1,010 |
| Extras | £250 tanking + 4 m² × £25 levelling + £60 trims and sealing | £410 |
| Labour total | £1,010 + £410 | £1,420 |
| Days tiling | 18 ÷ 8 + 4 ÷ 8 = 2.75, rounded up to the half day | 3 days |
| Earns per day | £1,010 ÷ 3 days | £337 |
£337 a day is in line with a £300 day rate, so the price works. Put the same figures into the calculator above and you'll get the same answer. The extras are left out of the per day figure on purpose: tanking and levelling have their own costs and drying time, so they're priced on their own.
On a small job the sum often comes out well below your day rate, because the setting up and cutting take as long as on a big one. That's what the minimum charge is for. For a full bathroom quote with materials, see how to quote a bathroom tiling job.